The Week of January 24-28, 2005

The Week of January 17-21, 2005

Workers installed exterior brass handrails at the south plaza entrance. They installed blinds and shades on the windows. Irrigation work continued and sod was laid on the south and west sides of the building. Workers began constructing the stage in the history classroom. Final cleaning started on the first floor following inspection by the architects.

The Week of January 10-14, 2005

Landscapping and irrigation work continued on the southside of the building. Insulation and duct rough-in continued on the third floor. Sheetrock and finish work contiuned in the third floor restroom. Marble was installed at RC1 door. Electrical wire mold rough-in continued on the existing third floor. Workers painted the ceiling inthe history classroom. Punchlist work continued throughout.

The Week of January 3-7, 2005

Rough-in duct work and insulation continued on third floor. Security rough-in work occurred on the third and other floors. Drywall work continued on the third floor. Workers poured forms for curbs in the Adams Avenue parking lot. An irrigation system was instaled at the H&R building and sod was laid also. The sprinkler system also started at Adams and Union St. Backfill and crusher-run spread at parking lot in preparation for re-paving. Electrical rough-in continued throughout. Columns were being set in the history classroom. Jesco started demo at door 125 into existing auditorium. Trim work continued on the third floor. The first coat of paint on the ceiling in the history classroom started. Doors were hung throughout the building.



Updated: February 1, 2005
http://www.archives.state.al.us/whatsnew/Jan05.html
Alabama Department of Archives & History
624 Washington Avenue
Montgomery, Alabama 36130-0100
Phone: (334) 242-4435
E-Mail:mark.palmer@archives.alabama.gov